Please see NOTICE below with additional information included for any issues.
Thank you,
Lisa Stacey
Administrative Assistant to Department Head
Purdue University
School of Materials Engineering
Neil Armstrong Hall of Engineering
765/494-4095
staceyl@purdue.edu

From: Qualio, Phillip H <pqualio@purdue.edu>
Sent: Friday, May 24, 2019 2:42 PM
To: Sondgerath, William J <wsondgerath@purdue.edu>; Shih, Tom I-P. <tomshih@purdue.edu>; Sherwood, Audrey H <asherwo@purdue.edu>; Bahr, David F <dfbahr@purdue.edu>; Stacey, Lisa A <staceyl@purdue.edu>; Coar, Stacey L <scoar@purdue.edu>; Riley, Donna
M <riley@purdue.edu>; Hays, Cindey A <isenberg@purdue.edu>; Oakes, William C. <oakes@purdue.edu>; Brown, Pamela R <pamb@purdue.edu>; Holloway, Elizabeth M <holloway@purdue.edu>; Mikels, Dawn J <djmikels@purdue.edu>; Gleghorn, Virginia L <vboothgl@purdue.edu>;
Dickerson, Darryl A <ddickerson@purdue.edu>; Bowker, David T <dbowker@purdue.edu>; Elias, Lindsay M <lindsaye@purdue.edu>; ARMS Business Office <eboarms@purdue.edu>
Cc: Reehling, Ronald E Jr <rereehling@purdue.edu>; Ticen, Kerry L <kticen@purdue.edu>
Subject: FW: NOTICE - LAF C.40.10449 Fiber Network Update - Group 1 Risers (5/28/19 – 8/2/19)
The following NOTICE from Physical Facilities is in regard to a campus-wide project taking place May 28th to August 2nd, 2019.
As indicated in red, no disruptions to the existing ITaP network are expected unless scheduled ahead of time. Full details can be found below.
Thanks,
Phil Qualio
Building Deputy
Neil Armstrong Hall of Engineering
Potter Engineering Center
(765) 496-9757
From: Reehling, Ronald E Jr <rereehling@purdue.edu>
Sent: Thursday, May 23, 2019 2:46 PM
Subject: NOTICE - LAF C.40.10449 Fiber Network Update - Group 1 Risers (5/28/19 – 8/2/19)
To: Building Deputies (Please distribute to: Department Heads, Directors)
Zone Leaders
From: Ron Reehling, Construction Project Manager, Senior
Capital Program Management
Re: LAF C.40.10449 Multiple Buildings Network Fiber Installation – Group 1 Risers (5/28/19 – 8/2/19)
This notification is to inform building occupants about the Multiple Buildings Network Fiber Installation project work occurring within your building from approximately May 28th-August 2nd, 2019. It is imperative that
this notification be shared with all Departmental Staff within each building.
PROJECT SCOPE:
IMPORTANCE OF THIS NOTIFICATION:
CHAIN OF COMMAND:
NON-EMERGENCY ISSUES/QUESTIONS:
At any time during construction, please feel free in contacting me with questions or concerns regarding the project.
Ronald E. Reehling, Jr. P.E.
Construction Project Manager, Senior
Physical Facilities, Capital Program Management
Purdue Technology Center Aerospace (PTCA)
1801 Newman Rd. Ste. 208
West Lafayette, IN 47906-4510
765-496-6379 / rereehling@purdue.edu