Good Afternoon, We have a crane pick tentatively scheduled for Wednesday 4/1/2026 in Lot 77 on the North side of the ET Building. We are in need to capture the Fire Lane and Parking Spaces, however I’m not 100% certain at this time, as to how many of the parking spaces are needed. It will also cut off some access to the Lab overhead doors located on that side of ET. We don’t anticipate anymore than a day to get the equipment to its final resting spot.
We should be receiving a lift plan in the very near future to finalize any details, however no other Building Closure should be needed.
Regardless if you could review the attached capture plan and let me know if you have any questions or concerns, we will be sure to get them addressed.
Thanks, Dino – IU CPF Construction