All,
Since we have our own separate boiler for the autoclave, this shutdown should
not affect use of the LORRE autoclave.
The only likely impact on LORRE is lack of hot water in the bathrooms and kitchen sink in 236 until the steam is restored.
Nate
--------------------------------------------
Nathan Mosier
Professor
Indiana Soybean Alliance Soybean Utilization Endowed Chair
Department of Ag. and Bio. Engineering
http://engineering.purdue.edu/ABE/
Laboratory of Renewable Resources Engineering
http://www.purdue.edu/lorre/
Potter Engineering Center, Room 220
500 Central Dr.
Purdue University
West Lafayette, IN 47907
(765) 494-7022 (phone)
mosiern@purdue.edu
--------------------------------------------
From: LORRE-list [mailto:lorre-list-bounces@ecn.purdue.edu]
On Behalf Of Carie, Carla S.
Sent: Wednesday, July 06, 2016 11:04 AM
To: lorre-list@ecn.purdue.edu
Subject: [LORRE-list] FW: POTR High Pressure Steam Shutdown
Importance: High
To All – FYI. Please see e-mail trail below regarding Steam Shutdown beginning today at noon through Friday at 5:00 PM.
Thank you,
Carla Carie
Administrative Assistant to the Director
Laboratory of Renewable Resources Engineering
Purdue University
500 Central Drive
West Lafayette, IN 47907-2022
Phone: 765-494-7022
Fax: 765-494-7023
E-mail:
carie@purdue.edu
From: Qualio, Phillip H
Sent: Wednesday, July 06, 2016 11:01 AM
To: Albrecht, Barbara S <balbrech@purdue.edu>; Alsup, Tina M <alsup@purdue.edu>; Arun Giridhar (agiridha@ecn.purdue.edu) <agiridha@ecn.purdue.edu>;
Carie, Carla S. <carie@purdue.edu>; Deputy, Dianna L. <deputyd@purdue.edu>; Duket, Steven D <sduket@purdue.edu>; Finney, Patricia Jean <pfinney@purdue.edu>;
Fosmire, Michael J. <fosmire@purdue.edu>; Foster, Vicki L <vlfoster@purdue.edu>; Gill, Amanda S <gill3@purdue.edu>; Haas, Rachel Luann <rachel@purdue.edu>;
'Hassanein, Ahmed' <hassanein@purdue.edu>; Johnson, Mark C <mcjohnso@purdue.edu>; Landry, Steven J <slandry@purdue.edu>; Reece, Kellie
A <kreece@purdue.edu>; Reklaitis, Gintaras V <reklaiti@purdue.edu>; Robinson, Nina L <nlrobins@purdue.edu>; Shade, Steven A <sashade@purdue.edu>;
'Shin, Yung' <shin@purdue.edu>; Van Epps, Amy S <vanepa@purdue.edu>; Wassgren, Carl R <wassgren@purdue.edu>;
xingya@purdue.edu; Kreke, Thomas R <tkreke@purdue.edu>; Mosier, Nathan S <mosiern@purdue.edu>
Cc: Barr, Robert L <rlbarr@purdue.edu>; Harrington, Jared R <jrharrin@purdue.edu>; Jewell, Patrick R <prjewell@purdue.edu>; Minjares,
Sarita <sminjare@purdue.edu>; Ticen, Kerry L <kticen@purdue.edu>; Ahlen, Donna J <ahlendj@purdue.edu>; Meister, Rustin R <rrmeister@purdue.edu>
Subject: FW: POTR High Pressure Steam Shutdown
Importance: High
All — please see the notice from Physical Facilities below regarding an unexpected STEAM SHUTDOWN for POTTER.
This will affect building HVAC, hot water and possibly some laboratory equipment, such as Autoclave’s.
Thanks,
Phil Qualio
Building Deputy
Neil Armstrong Hall of Engineering
Potter Engineering Center
765.496.9757 — 765.494.7020
From: Kult, Larry E
Sent: Wednesday, July 06, 2016 9:57 AM
Cc: Qualio, Phillip H
Subject: POTR High Pressure Steam Shutdown
PHYSICAL FACILITIES
ENERGY AND CONSTRUCTION
FR:
Larry Kult
DA:
July 6, 2016
RE:
POTR High Pressure Steam Shutdown
Building(s) Affected: POTR (Potter (A.A.) Engineering Center)
Utility Shutdown Notice:
This notification is for a high pressure steam shutdown POTR. The purpose of this shutdown is to facilitate construction activities for the Centennial Mall Sitescape & Utility
Tunnel Repair - 2016 project.
Date/Time of Shutdown: 12:00pm Wednesday, July 6, 2016 to 5:00pm Friday, July 8, 2016
Shutdown Requestor/Contact:
Rustin Meister, rrmeister@purdue.edu, 765-496-9477