Notice:

There is a change of plans that reduces the amount of time that vibration events will take place at the BNC.

 

Work today, Friday, 20 May 2016, will continue until 5:00 pm. Please note that there will be vibration-creating activities until 5:00 pm today. We expect to cancel the vibration alert for next Monday and Tuesday.

 

We will keep everyone updated.

 

John

 

 

John R. Weaver

Strategic Facilities Officer

Birck Nanotechnology Center

1205 West State Street

West Lafayette IN 47907

(765) 494-5494

jrweaver@purdue.edu

nano.purdue.edu

 

 

 

From: Denecke, Jacob M
Sent: Friday, May 20, 2016 2:01 PM
To: 'Tom Lernihan' <TLernihan@pepperconstruction.com>; Nikolaidis, Natasha N <nnikolai@purdue.edu>; Rudolph, Stephen G <sgrudolph@purdue.edu>; Schlegel, Sylvia L <sschlege@purdue.edu>; Shakouri, Ali <shakouri@purdue.edu>; Standifer, Anthony N <anstandifer@purdue.edu>; Voorhis, Mark L. <mvoorhis@purdue.edu>; Weaver, John R <jrweaver@purdue.edu>
Cc: Yuvaraaj S <yuvaraaj@pepperconstruction.com>; Chris Rayner <CRayner@pepperconstruction.com>; Nicholas Abrams <NAbrams@pepperconstruction.com>; McKinsey O'Neil <mckinseyoneil@pepperconstruction.com>
Subject: RE: Flex Lab Facility - Notice of Vibration *CORRECTION*

 

All,

 

Are there any objections to Pepper working till 5:00 PM today to install the remaining H-piles?  This would mean we would not be driving H-piles next week and could cancel the high vibration notice for next week. 

 

Regards,

 

Jake Denecke, P.E.

Capital Project Manager

 

Purdue University

Energy & Construction

Ph: 765.494.6721 | Fax: 765.494.0918 | Cell: 815.762.2397

 

From: Tom Lernihan [mailto:TLernihan@pepperconstruction.com]
Sent: Friday, May 20, 2016 9:53 AM
To: Nikolaidis, Natasha N <nnikolai@purdue.edu>; Rudolph, Stephen G <sgrudolph@purdue.edu>; Schlegel, Sylvia L <sschlege@purdue.edu>; Shakouri, Ali <shakouri@purdue.edu>; Standifer, Anthony N <anstandifer@purdue.edu>; Voorhis, Mark L. <mvoorhis@purdue.edu>; Weaver, John R <jrweaver@purdue.edu>; Denecke, Jacob M <jdenecke@purdue.edu>
Cc: Yuvaraaj S <yuvaraaj@pepperconstruction.com>; Chris Rayner <CRayner@pepperconstruction.com>; Nicholas Abrams <NAbrams@pepperconstruction.com>; McKinsey O'Neil <mckinseyoneil@pepperconstruction.com>
Subject: RE: Flex Lab Facility - Notice of Vibration *CORRECTION*

 

All,

 

CORRECTION: My previous email issued a notice for April, in lieu of May. Sorry for the mistake.

 

Vibration Update:

-        High vibration and Noise should be expected on the following dates & times:

o   Friday, May 20th – 7:00 AM – 3:30 PM

o   Monday, May 23rd – 7:00 AM – 3:30 PM

o   Tuesday, May 24th – 7:00 AM – 3:30 PM

 

Thanks,

 

Tom Lernihan, LEED® AP BD+C
Project Manager

Pepper Construction of Indiana /// BREAKING GROUND
Illinois . Indiana . Ohio

M 317-557-7330

 

From: Tom Lernihan
Sent: Friday, May 20, 2016 9:43 AM
To: 'Nikolaidis, Natasha N'; 'Rudolph, Stephen G'; 'Schlegel, Sylvia L'; 'Shakouri, Ali'; 'Standifer, Anthony N'; 'Voorhis, Mark L.'; 'Weaver, John R'; 'Denecke, Jacob M'
Cc: Yuvaraaj S; Chris Rayner; Nicholas Abrams; McKinsey O'Neil
Subject: Flex Lab Facility - Notice of Vibration

 

All,

 

The construction project has run into an issue yesterday afternoon and we will need to extend the notice for high vibration activities through next Tuesday the 24th. Our apologies for the last minute extension, we are having difficulty locating existing underground utilities, and subsequently it has delayed our Earth Retention installation.

 

Vibration Update:

-        High vibration and Noise should be expected on the following dates & times:

o   Friday, April 20th – 7:00 AM – 3:30 PM

o   Monday, April 23rd – 7:00 AM – 3:30 PM

o   Tuesday, April 24th – 7:00 AM – 3:30 PM

 

Thanks,

 

Tom Lernihan, LEED® AP BD+C
Project Manager

Pepper Construction of Indiana /// BREAKING GROUND
Illinois . Indiana . Ohio

M 317-557-7330

 

From: Tom Lernihan
Sent: Friday, May 06, 2016 9:38 AM
To: 'Nikolaidis, Natasha N'; 'Rudolph, Stephen G'; 'Schlegel, Sylvia L'; 'Shakouri, Ali'; 'Standifer, Anthony N'; 'Voorhis, Mark L.'; 'Weaver, John R'; 'Denecke, Jacob M'
Cc: Yuvaraaj S; Chris Rayner; Nicholas Abrams
Subject: Flex Lab Facility - Notice of Vibration & Gates Road Work

 

All,

 

We wanted to provide an update to all of the adjacent buildings to the Flex Lab Facility that the following work will occur:

 

Vibration Update:

-        Our contractors are expected to start the installing of the earth retention along the North side of Gates Road on Thursday May 12th This work will include the use of a vibratory attachment to an excavator to drive steel beams down 30’ into the ground.

-        High vibration and Noise should be expected on the following dates & times:

o   Thursday, May 12th – 7:00 AM – 3:30 PM

o   Friday, April 13th – 7:00 AM – 3:30 PM

o   Monday, May 16th – 7:00 AM – 3:30 PM

o   Tuesday, May 17th – 7:00 AM – 3:30 PM

o   Wednesday, April 18th – 7:00 AM – 3:30 PM

o   Thursday, April 19th – 7:00 AM – 3:30 PM

o   Friday, April 20th – 7:00 AM – 3:30 PM

 

 

Gates Road Work Update

-        Gates Road will remain open for full use of Truck and Vehicle traffic until Monday, May 9th 2016.

 

-        On Monday May 9th, fencing will be relocated, per the attached plan, that will prohibit delivery access to the Birck Nontechnology Center via Gates Road

o   Delivery to Bindley and Discovery Learning center will remain open at all times via Gates Road.

o   This revised fencing plan will remain in place for 6 – 12 months.

 

Please let us know if there are any issues with this plan.

 

Thanks,

 

Tom Lernihan, LEED® AP BD+C
Project Manager

Pepper Construction of Indiana /// BREAKING GROUND
Illinois . Indiana . Ohio . Texas

T 317-681-5257

M 317-557-7330